Four Auckland stadiums need nearly $300m just to stand still, plan says
Auckland’s four main stadiums need nearly $300 million spent on them over the next decade to stay at their current standard, a new council plan shows.
About $122m of that is for Eden Park, whose problems are described as a “burning platform” in the Playing to Our Strengths report.
Auckland Council’s plan aims to better integrate the city’s stadium network, focusing on the big four: Eden Park, Go Media Stadium, North Harbour Stadium and Western Springs Bowl.
The plan goes before the council’s value for money committee today, with councillors asked to endorse it as the council’s strategic framework. No money is committed until the 2027–2037 Long-term Plan.
Tātaki Auckland Unlimited, which runs Go Media Stadium, North Harbour Stadium and Western Springs Bowl, puts the cost of keeping those three venues at their current level at $178m over 10 years.
Go Media Stadium at Mt Smart makes up the majority of the cost at $127m, which is more than three times the $38m allocated in the previous long-term plan.
The higher figure covers renewals and the first stage of a masterplan of improvements for the stadium, including work on the west stand.
North Harbour needs $33m over 10 years, the same as it was allocated in the previous long-term plan, while Western Springs needs $17m, down from $21m.
A burning platform
The plan’s section on the national stadium is headed: “Problems we are seeking to solve – a burning platform”.
Eden Park faces about $122m in maintenance and renewals over the next 10 years, a bill the plan says can’t be sustainably met from its operating surpluses.
The council also has a $54m loan facility with the trust, due for repayment in September 2029.
In the report, the council does not commit to paying the bill.
Under Eden Park’s current governance model, the council will not inject more money or loan relief into the stadium.
“Any future contribution could be additional to Tātaki’s stadium investment envelope or require reprioritisation within the wider stadium network,” a supplementary document to the report reads.
In response to Herald questions, Eden Park Trust did not say whether it agreed with the burning platform description or who it expected to fund the $122m.
The stadium received no operational funding from the council or the Government.
“We acknowledge that parts of our infrastructure are ageing and have provided a high-level summary of a proposed long-term renewals programme, alongside the role public funding can play in supporting an asset whose benefits extend well beyond its gates.”
The report outlines that because of Eden Park’s separate ownership, the major stadiums had operated in competition that is not always best for Auckland.
However, first steps towards fixing that were underway by releasing the park from historical restraints and negotiating new governance models.
The Foundation Agreement, signed this year by the council, the Crown, Eden Park Trust, Auckland Cricket and Auckland Rugby, sets a pathway for both codes to leave the ground they have called home for more than a century.
“Auckland Cricket and Auckland Rugby’s rights constrain Eden Park’s flexibility, commercial opportunities and case for public investment,” the plan says.
Cricket is moving to Colin Maiden Park, while rugby’s new home is yet to be settled.
Cricket’s move will also free up options for developing other uses of the outer oval land, although what that might be has not been decided.
The Foundation Agreement includes a precinct plan integrating Eden Park with Kingsland, and the plan calls for wider planning along the Morningside to Maungawhau corridor.